FCC Licenses SpaceX’s Starmind: What the One Million Satellite Order Grants, Defers and Refuses to Decide

The FCC's Starmind order lets SpaceX deploy up to one million orbital data centre satellites. What it grants, what it defers and what it says it cannot decide.

On 5 November I wrote that four orbital data centre applications were sitting at the FCC and none had been granted. Three weeks later the largest of them has been. The Space Bureau has authorised SpaceX to deploy up to one million satellites under the name Starmind, more than any operator has ever been licensed to fly.

The legal interest is in the detail: what the FCC licensed, which rules it waived, what it postponed, and what it said it has no power to consider.

What the FCC granted

The decision is a combined grant and Memorandum Opinion and Order, DA 26-1273, adopted and released on 25 November 2026 by Courtney Reinhard, Chief of the Space Bureau, under delegated authority. The licensee is Space Exploration Holdings, LLC, the application is ICFS File No. SAT-LOA-20260108-00016 and the call sign is S00798. The Bureau had accepted the application for filing on 4 February 2026.

The scope of grant is “radiofrequency communications for backup and emergency telemetry, tracking, & command (TT&C) for a constellation of 1,000,000 NGSO satellites to operate as data centers in space.” That is the whole of it. The FCC does not license computing, power generation or anything else the satellites do. It licenses the radios.

The authorised bands are 18.8 to 19.3 GHz (space-to-Earth) and 28.6 to 29.1 GHz (Earth-to-space). SpaceX told the Bureau that it does not plan to use them except to support limited emergency operations, because each satellite will rely on optical links within the constellation and to its Starlink satellites. If a Starmind satellite does need to use radio, it will talk to Starlink gateway earth stations, and the order says SpaceX must obtain the necessary earth station authorisations first.

The orbits are narrower than SpaceX first asked for. The February public notice described shells from 500 to 2,000 km. The grant covers shells of up to 50 km each at altitudes from 500 to 1,002 km, at 30-degree and sun-synchronous inclinations, with nominal operating bands such as 550 to 568 km and 967 to 1,002 km.

The waivers: why one million satellites needed so many

The order grants four waivers, and they explain how a constellation of this size fits rules written for far smaller systems.

The first is a waiver, on the Bureau’s own motion, of the US Table of Frequency Allocations. Both Ka-band segments are allocated to the Fixed-Satellite Service, and whether standalone TT&C counts as Fixed-Satellite Service is a question the full Commission is still considering in its “Weird Space Stuff” rulemaking. Rather than decide that question at Bureau level, it waived the table for SpaceX.

The second is a waiver of the processing round rules in sections 25.156 and 25.157. Normally a new non-geostationary application triggers a processing round in which competitors can file. Here the Bureau said SpaceX gets no priority from the waiver and must protect operators licensed in earlier and later rounds.

The third and fourth deal with surety bonds and milestones. SpaceX originally asked to be freed from milestones altogether, then withdrew that request in October and asked instead for the new milestone schedule the Commission adopted in its July Space Modernization order, which I covered in our note on Part 100 milestones and surety bonds. The Bureau agreed. The authorisation becomes void unless SpaceX:

  • deploys and operates one satellite by 25 November 2033;
  • deploys 10% of the authorised number by 25 November 2035;
  • deploys 50% by 25 November 2038; and
  • completes the constellation by 25 November 2040.

The surety bond requirement was waived outright. The licence term is 15 years, starting when SpaceX certifies that its first Starmind satellite is in orbit and operating in line with the grant.

Several commenters, including Secure World Foundation and DarkSky International, argued that so many waivers in one application stripped away every guardrail on an untested technology. The Bureau’s answer was that nothing in the rules limits the number of waivers an applicant may ask for, and it pointed to earlier grants for novel missions, including Reflect Orbital’s space mirror licence.

What was deferred: disposal above 600 km

The most important limit in the grant is condition 4. FCC rules require a satellite that ends its mission below 2,000 km to be disposed of by atmospheric re-entry “as soon as practicable, but no later than five years following completion of the mission.” That is the five-year deorbit rule adopted in 2022.

SpaceX asked for flexibility to send satellites operating above 600 km into “Earth disposal orbits or heliocentric orbits” instead. The Bureau did not refuse that request. It deferred it, because SpaceX had not given enough information to show the alternatives comply. Before deploying any Starmind satellite that will not be disposed of by re-entry, or any satellite above 600 km, SpaceX must file a modification application with a final orbital debris mitigation plan.

Some early coverage called this a denial. It is a postponement, and it matters because four of the six nominal operating shells sit above 600 km. In practice, SpaceX can start in the lowest shells now and must come back for the rest.

For satellites below 600 km, the Bureau found the debris plan compliant. SpaceX committed to testing satellites at lower altitudes first, to propulsion for raising, station-keeping and disposal, to controlled de-orbiting with re-entry steered over the ocean, and to a design that “fully demises during reentry.” The Bureau also added a semi-annual reporting condition covering conjunction events, failed satellites, re-entries and deployed numbers, due by 1 January and 1 July each year.

On congestion, the Bureau was blunt. Commenters worried about the sheer number of satellites, but “the Commission’s rules do not place limits on the number of space stations that can be authorized with similar orbital parameters and the Space Bureau declines to invent a de facto rule in this adjudicatory licensing proceeding.”

Newsletter

Get Space Law Insider every Monday

One short email a week with the space law news and analysis worth your time. Free, and you can leave any time.

Weekly, free, no spam. Unsubscribe any time. Privacy policy

What the Bureau said it cannot decide

The last part of the order is the one I expect to be litigated. The Bureau dismissed a set of objections as outside the FCC’s authority.

On the environment, it relied on the Commission’s October 2026 NEPA order, which found that licensing space-based operations is not a major federal action because the activities are “extraterritorial”. That rule was published in the Federal Register on 17 November 2026 and takes effect on 17 December 2026 for most provisions. The Bureau said that even under the current rules it would not require further review. It added that launch emissions are for the FAA, and that concerns about satellites burning up on re-entry “remain speculative and not supported in the record.” I analysed the NEPA order in our piece on the FCC’s finding that satellites are not a major federal action.

On optical astronomy, the Bureau said SpaceX’s commitment to coordinate with the National Science Foundation was enough, that the grant had been coordinated through NTIA with NASA, NOAA and federal astronomy bodies, and that the FCC’s rules do not address optical astronomy. The American Astronomical Society’s argument that waste heat from a million data centres would raise the infrared background of the sky was treated as a non-spectrum issue outside the review.

On doubts about whether orbital data centres work or are needed, the Bureau said such concerns “are not obviously related to the limited mandate given by Congress to the FCC to regulate radiocommunications”.

The petitions to deny filed by Kuiper Systems (Amazon Leo), Viasat and the American Astronomical Society were all denied.

My reading of the order

The order is internally consistent with the FCC’s position that it “licenses the use of spectrum, not facilities”, a phrase I quoted in our explainer on the law on orbital data centres. If radio is the hook, a system that barely uses radio needs very little licensing. That is exactly what Starmind received.

The difficulty is that radio is also the only real federal hook. No US agency licenses computing in orbit, and the FAA’s payload review is limited. So the logic of the order means that the largest constellation ever authorised is approved after a review confined to backup telemetry, with debris above 600 km deferred and the atmosphere, astronomy and congestion treated as someone else’s problem. Article VI of the Outer Space Treaty requires the activities of US companies in space to have “authorization and continuing supervision” by the United States. Whether a radio licence of this scope is enough to discharge that duty is a fair question, and the order does not engage with it.

Two points cut the other way. The milestone schedule is a real constraint: if SpaceX does not have 100,000 satellites working by November 2035, the authorisation fails. And the semi-annual reports will give the FCC, and the public, the first hard data on how a data centre constellation behaves.

What I would watch

The first date is around 25 December 2026. The grant gives SpaceX 30 days from release to decline it as conditioned, and Amazon, Viasat or the astronomers have 30 days from public notice of the action to file an application for review by the full Commission under 47 CFR 1.115. A Commission vote would be the next step before any court challenge.

The second is the modification application for satellites above 600 km. Whether the FCC accepts heliocentric disposal, or any alternative to atmospheric re-entry, will set a precedent for every high-altitude constellation that follows.

The third is the other orbital data centre applications. The order says the FCC is reviewing more and intends to decide them on the same basis. If Starcloud, Blue Origin and others receive similar grants, the NEPA question will be raised again, and Earthjustice, acting for DarkSky International and others, has already said it is prepared to sue.

The fourth is international. Condition 5 requires SpaceX to operate consistently with its ITU filings, which other administrations will now examine closely.

Questions people actually ask


What is SpaceX Starmind?

Starmind is the name of SpaceX’s proposed constellation of up to 1,000,000 satellites designed to operate as data centres in low Earth orbit. The satellites are meant to communicate mainly by laser with each other and with Starlink, using radio only for backup and emergency control.


Did the FCC approve one million SpaceX satellites?

Yes, in part. On 25 November 2026 the FCC’s Space Bureau granted SpaceX authority for backup and emergency telemetry, tracking and command radio for a constellation of up to 1,000,000 satellites at 500 to 1,002 km, in order DA 26-1273. It deferred any satellites above 600 km until SpaceX files a final debris plan.


When does SpaceX have to launch the Starmind satellites?

Under the milestones applied in the order, SpaceX must have one satellite operating by 25 November 2033, 10% of the constellation by 25 November 2035, 50% by 25 November 2038 and the full constellation by 25 November 2040. If it misses a milestone, the authorisation becomes void.


Did the FCC consider the environmental impact of Starmind?

No. Relying on its October 2026 NEPA order, the FCC said that licensing space-based operations is not a major federal action, so no further environmental review was required. It said launch emissions are for the FAA and described concerns about satellites burning up on re-entry as speculative.


Can the Starmind licence be challenged?

Yes. Petitioners can ask the full Commission to review a Bureau decision by filing an application for review within 30 days of public notice of the action under 47 CFR 1.115. A decision of the full Commission can then be challenged in a federal court of appeals.


Who objected to the Starmind application?

Kuiper Systems (Amazon Leo), Viasat and the American Astronomical Society filed petitions to deny, and many others commented, including Secure World Foundation and DarkSky International. The Space Bureau denied all three petitions.


Space Law Insider

Read the week in space law in five minutes

Every Monday we send one email with the new regulations, filings, cases and explainers published on Space Law Journal. Join practitioners, students and policy people who read it.

Weekly, free, no spam. Unsubscribe any time. Privacy policy

Astronomy FCC Licensing NEPA Orbital data centres Orbital debris SpaceX
Anuj Kumar

Anuj KumarEditor-in-Chief

Anuj Kumar is the founder of Legal Desire Media and publishes Fashion Law Journal and Space Law Journal.

Space Law Journal is a joint initiative of Legal Desire Media and Odyogeek. Spotted something we got wrong, or want to respond? Write to space@legaldesire.com.

Keep reading

Related from the journal

More regulatory updates

Have something to say on this?

We publish responses, case notes and analysis from practitioners, academics and students.

Submit Follow