Upper C-Band Relocation Coordinator: Satellite Operators Pick RSM as the FCC Opens Comment
SES, Eutelsat and Telesat chose RSM as Upper C-band relocation coordinator on 17 November 2026. What the role covers, who pays and the 3 December comment date.
The Upper C-band transition now has a referee. On 17 November 2026 the three satellite companies that must move their services out of most of the 4 GHz band told the Federal Communications Commission they had picked RSM US LLP as Relocation Coordinator. The next day the FCC asked the public whether RSM is qualified.
It is a procedural step, but the coordinator will turn the operators’ Transition Plans into a working schedule for thousands of earth stations and will have a large say in when new 5G licensees can switch on. For the wider picture of the clearing plan and the $6.3 billion in incentive payments, see our earlier piece on the Upper C-band transition.
What was filed, and when
The FCC’s Upper C-band order, released on 24 July 2026, requires the “eligible space station operators” to select a Relocation Coordinator no later than 1 January 2027. For this transition those operators are Eutelsat, SES and Telesat.
On 17 November 2026 the operators filed a joint letter, signed for SES by Tom McNamara, its senior vice president for the C-band transition, announcing that they had selected RSM. On 18 November the Bureau released Public Notice DA 26-1248 seeking comment on whether RSM satisfies the criteria. A summary was published in the Federal Register on 24 November 2026 at 91 FR 75856.
The test is short. Under the order, the coordinator “must be able to demonstrate that it has the requisite expertise to perform the duties required in this context”. After the comment period the Bureau will issue a final order saying whether the criteria are met. If they are not, the selection committee starts again and the next candidate goes through the same comment process.
Why the transition has a Relocation Coordinator at all
The FCC is clearing 4.0-4.16 GHz of satellite downlinks in the contiguous United States so that it can auction 3.98-4.14 GHz for terrestrial wireless use, with a guard band at 4.14-4.16 GHz and satellites keeping 4.16-4.2 GHz. The order, published in the Federal Register on 31 July 2026, chose to run the clearing as an “eligible space station operator-led process, which will be facilitated by a Relocation Coordinator”.
The satellite operators decide how to move their own customers. A separate Upper C-band Clearinghouse deals with money: reimbursement claims, lump sums and radio altimeter rebates. The coordinator makes sure the physical work happens in the right order and on time.
One difference is easy to miss. The rules define the clearinghouse as “a neutral, independent third-party”, but the FCC found it “unnecessary for the Relocation Coordinator to be a neutral third-party”, because earth station owners who take a lump sum handle their own transition. The Commission said it “retains its oversight functions” over the coordinator.
What the coordinator will actually do
The duties are set out in section 27.1413 of the FCC’s rules, which you can read on eCFR, and in the order itself. The core list is:
- coordinating the schedule for clearing 4.0-4.16 GHz;
- performing engineering analysis to decide what migration work each earth station needs, such as retuning or repointing antennas;
- assigning responsibility for earth stations that no operator’s Transition Plan covers, or setting out an individual Earth Station Transition Plan for them;
- coordinating with the new Upper C-band licensees throughout;
- assessing and tracking completion in each Partial Economic Area and determining when wireless licensees can start operating;
- mediating scheduling disputes.
The order adds more. The coordinator may review the operators’ Transition Plans and recommend changes to the Commission. It receives complaints from earth station operators and other satellite customers about “comparability of facilities, workmanship, or preservation of service”, passes them to the Bureau and recommends a resolution. It must file public quarterly status reports, two weeks after the operators file theirs, and attend regular status meetings with FCC staff. Satellite operators and earth station operators must “cooperate in good faith” with it, and it with them.
There is also an auction duty. While the FCC’s anti-collusion rule applies to Auction 115, the coordinator must “disclose in real time the content of, timing of, and parties to” any communications with auction applicants, a real constraint when it will be discussing clearing schedules with mobile carriers planning their bids.
Who pays for the coordinator
The answer depends on who appoints it. If the operators’ choice is confirmed, “each eligible space station operator will be responsible for paying the Relocation Coordinator’s costs based on its pro rata share of the total amount of incentives”. The order split the incentive payments 89% to SES, 8% to Eutelsat and 3% to Telesat, with maximum amounts of $5.607 billion, $504 million and $189 million. On that formula SES would carry most of the coordinator’s bill.
If the committee fails to select a coordinator that meets the criteria by 1 January 2027, the committee is dissolved, the FCC’s Office of the Managing Director runs a procurement, and the new Upper C-band licensees pay the coordinator’s reasonable costs through the clearinghouse, in the same pro rata way as the clearinghouse’s own costs.
One technical point. Several parts of section 27.1413, including the operator cost rule, the duty to review Transition Plans, the dispute role and the quarterly reports, contain information collections that do not take effect until the Office of Management and Budget approves them and the FCC publishes an effective date. The effective-date notices published on 19 and 29 October 2026 covered the Transition Plan rule and the lump sum rule, not these parts of section 27.1413. I would expect that notice before RSM starts real work, but it has not appeared yet.
Newsletter
Get Space Law Insider every Monday
One short email a week with the space law news and analysis worth your time. Free, and you can leave any time.
RSM has done this before
The choice is not a surprise. In the Lower C-band transition, which cleared 3.7-3.98 GHz, the five eligible satellite operators announced on 31 July 2020 that they had selected RSM. On 25 September 2020 the Bureau found that RSM met the criteria, noting in its order that “No commenters opposed RSM’s selection.” CohnReznick served as the clearinghouse in that transition.
According to the Upper C-band order, all five operators met their accelerated deadlines, the practical work finished in 2023 and the reimbursement programme ended on 21 August 2025. The FCC wants a coordinator with “similar qualifications and responsibilities to those established in the Lower C-band context”, so continuity was probably the point of the choice.
Where this sits in the timetable
The coordinator notice is one of several steps landing in a short window:
- 5 November 2026: Transition Plans due. SES said in its third-quarter results that its plan would be submitted that day.
- 13 November 2026: the FCC adopted the Auction 115 procedures: 3,248 licences, a clock phase followed by an assignment phase, and bidding from 27 April 2027.
- 30 November 2026: comments due on the operators’ Transition Plans in the new GN Docket No. 26-289.
- 3 and 14 December 2026: comments and replies on RSM.
- 15 December 2026: deadline for the clearinghouse selection committee to tell the FCC its choice. Proposals were due on 9 November.
- 1 January 2027: fallback date for the coordinator, after which the FCC procures one itself.
- 6 to 20 January 2027: short-form application window for Auction 115, according to the FCC’s 13 November announcement.
- 30 December 2030 and 30 June 2031: the primary and final transition deadlines.
The auction notice shows why the coordinator matters to bidders. The FCC declined a request to prepare “a consolidated summary of information from multiple dockets concerning known incumbent sites, anticipated clearing timelines, and continuing federal or satellite operations”. Bidders must do their own due diligence, and the coordinator’s schedule and quarterly reports will be a main public source for it.
What it means for earth station owners and bidders
For cable operators, broadcasters and others who receive C-band feeds and have not taken the lump sum, the coordinator is the body to deal with. It can assign an orphaned earth station to an operator, set its migration steps and hear complaints about the replacement service. Owners who take the lump sum leave that system and must meet the deadline on their own.
For bidders, the coordinator decides when the band is clear in each market, which is when service can start. Its real-time disclosure duty during the auction quiet period also means any contact with it should be planned with counsel.
For the satellite operators, the choice is about control. They selected the coordinator, they will pay for it, and it need not be neutral. The 2020 precedent suggests this works, but I would expect wireless interests to ask for safeguards on conflicts and information sharing.
The Upper C-band sits alongside the FCC’s decision to open 12.7 GHz and 42 GHz to satellites and the 1675-1695 MHz auction. Because the FCC’s changes are national, any new satellites carrying services moved to Ku-band still go through the process in our explainer on ITU filings and orbital slots.
What I would watch
The first is the comment round closing on 3 December. If nobody objects, as in 2020, a quick final order is likely. A filing questioning RSM’s independence would slow things down.
The second is the effective-date notice for the rest of section 27.1413. Until it is published, parts of the coordinator’s role, including the cost rule and Transition Plan review, are adopted but not in force.
The third is the clearinghouse. Its selection is due by 15 December, and the coordinator and clearinghouse will have to work together closely, since one sets the schedule and the other decides what gets paid.
The fourth is the Transition Plan comments due on 30 November. The coordinator will inherit any argument that the plans are unrealistic.
Questions people actually ask
What is the Upper C-band Relocation Coordinator?
It is the body that manages the practical side of clearing satellite downlinks from 4.0-4.16 GHz in the contiguous United States. Under section 27.1413 of the FCC’s rules it schedules the clearing, decides earth station migration steps, tracks completion in each market, determines when new wireless licensees can start and mediates scheduling disputes.
Who was selected as Upper C-band Relocation Coordinator?
On 17 November 2026 the three eligible space station operators, SES, Eutelsat and Telesat, announced that they had selected RSM US LLP. The FCC’s Wireless Telecommunications Bureau is now taking comment on whether RSM meets the selection criteria before issuing a final order.
When are comments due on the Relocation Coordinator?
Comments are due on 3 December 2026 and reply comments on 14 December 2026, filed in GN Docket No. 25-59.
Who pays the Relocation Coordinator?
If the operators’ selection is confirmed, SES, Eutelsat and Telesat pay its costs in proportion to their shares of the incentive payments, which are 89%, 8% and 3%. If no coordinator is confirmed by 1 January 2027 and the FCC procures one, the Upper C-band licensees pay its reasonable costs through the clearinghouse.
Is RSM the same firm that coordinated the Lower C-band transition?
Yes. The Lower C-band satellite operators selected RSM on 31 July 2020, and the FCC confirmed on 25 September 2020 that it met the criteria, noting that no commenters opposed the selection. That transition finished its practical work in 2023.
Does the Relocation Coordinator handle earth stations that took the lump sum?
No. Earth station owners who elect the lump sum payment take responsibility for their own transition and must meet the deadline for their area. The FCC said the coordinator does not need to track their progress once they have filed their election.